New Middle School #6

MS6 Exterior 2-13-19
The new middle school will serve 900 students in grades 6-8. The 130,000 square foot building will help reduce student populations at five existing middle schools, accommodate student population growth and meet the District's needs into the future.

The Issaquah School District has been approved by the Capital Projects Advisory Review Board to use Progressive Design Build on this project.  The process brings the designer and builder team on earlier to help with a project's design and construction costs. The District feels this alternative process is well suited to the new high school project.

Middle School #6 will be a high performance building. The educational program will include core learning environments, a science suite, music, athletic facilities including an all-weather turf athletic field, community spaces (library, gym, Commons with stage and dining), administrative areas, special services and building support spaces.

The District has a purchase and sale agreement for approximately nine acres of property located at the entrance of the Talus community in Issaquah as the site of Middle School #6. Feasibility work including a pre-application submittal to the City of Issaquah is in progress.

Project Information
Original Project Estimate: $74,000,000
Project Budget: $74,000,000
Budget: $74,000,000
Explanation:
Funding source: 2016 Bond
Project status: Planning and/or Design
Architect: Integrus
Contractor: Cornerstone General Contractors
Estimated completion: September 2021

March 2019

  • School District and Design Build Team continuing to work with the City of Issaquah staff.

    • Expect to submit SDP package to City of Issaquah in the next few weeks.

  • School District and Design Build Team continuing to work with the building interior layout.

  • Building site and exterior plans submitted to the Talus Residential Association (TRA) Architectural Review Committee (ARC).  Expect review comments back soon.

  • GeoTech continuing with subsurface exploration.


January 2019

  • Design Build Team continuing with design of the site and the building.

  • The Team attended a second Pre-Application meeting with the City of Issaquah.

  • GeoTech continuing with subsurface exploration of the site.

  • Community meeting with both the Timber Ridge Retirement Community and Talus HOA was held and both had an overall positive response to the project.


September 2018

  • Design Build Team continuing with site feasibility study.


June 2018

The Design Build Team is working through the schematic design phase.

April 2018

Design Build team of Cornerstone General Contractors and Integrus Architecture was selected for the project.