Bond Projects

Maple Hills Expansion/Remodel

Maple
Remodel and potential expansion of existing building.
The Maple Hills Expansion and Remodel will provide modifications and potentially add classrooms to the existing building. An earlier office remodel was completed in 2016 to improve safety and security. Bus and vehicle drop-off areas were reconfigured to enhance safety and traffic flow prior to the 2017 school year.
Project Information
Original Project Estimate: $7,000,000
Project Budget: To Be Determined
Budget: To Be Determined
Explanation:
Funding source: 2016 Bond
Project status: Planning, Design, and/or Permitting
Architect: TBD
Contractor: TBD
Estimated completion: Summer 2021

October 2020

  • ISD and the Design Team continue to work with the Principal and Staff to refine the final design.
  • Work expected to include; full HVAC replacement, fire sprinkler system replacement, enclosed walkway to the gym area, exterior repaint and possibly some new limited room reconfigurations.
  • The painting of the exterior of the building is complete.
  • The permit application to King County has been submitted and the first round of review comments have been received and responded to.
  • Work expected to begin in Spring 2021 dependent upon permit issuance.

September 2020

  • ISD and the Design Team continue to work with the Principal and Staff to refine the final design.
  • Work expected to include; full HVAC replacement, fire sprinkler system replacement, enclosed walkway to the Gym area, exterior repaint and possibly some new limited room reconfigurations.
  • The painting of the exterior of the building is complete.
  • The permit application to King County has been submitted and the first round of review comments have been received and responded to.
  • Work expected to begin in the Spring 2021 dependent upon permit issuance.

August 2020

  • ISD and the Design Team continue to work with the Principal and Staff to refine the final design.
  • Work expected to include; full HVAC replacement, fire sprinkler system replacement, enclosed walkway to the Gym area, exterior repaint and possibly some new limited room reconfigurations.
  • The painting of the exterior of the building is complete.
  • The permit application to King County has been submitted.
  • Work expected to begin in late Spring dependent upon permit issuance.

June 2020

  • ISD and the Design Team continue to work with the Principal on design development and program needs.
  • Work expected to include; full HVAC replacement, fire sprinkler system replacement, enclosed walkway to the Gym area, exterior repaint and possibly some new limited room reconfigurations.
  • ISD is working with the Design Team and the Principal on potential color schemes for the exterior of the building. Building exterior to be painted over Summer 2020.

May 2020

  • ISD and the Design Team continue to work with the Principal on design development and program needs.
  • Work expected to include; full HVAC replacement, fire sprinkler system replacement, enclosed walkway to the Gym area, exterior repaint and possibly some new limited room configurations.
  • ISD is working with the Design Team and the Principal on potential color schemes for the exterior of the building.

April 2020

  • Capital Projects and Cornerstone Architectural Group are continuing with design development and meeting with staff on program needs, this is about 70% complete.
  • Capital Projects is working through various cost exercises to determine what the final budget will be for the construction of the project. HVAC and Fire Sprinkler upgrade needs are currently over half of the overall budget.

March 2020

  • Capital Projects and Cornerstone Architectural Group are continuing with design development and meeting with staff on program needs, this is about 65% complete.
  • CP and Design team are working with the Mechanical Engineer to locate boiler room and determine what HVAC system design is best for the school.
  • CP is working through various cost exercises to determine what the final budget will be for the construction of the project. HVAC and Fire Sprinkler upgrade needs are currently over half of the overall budget
No photos galleries are available for this project.
No additional documents are available for this project.