Liberty High School Addition and Modernization Phase II and III

LHS-P3-New Wing
With passage of the 2012 Bond, Phase II and III construction was approved to include reconfiguration of the office and counseling areas, an additional auxiliary gym, new classroom wings and a new Library.

Liberty High School Addition and Modernization Phase II includes: reconfiguration/expansion of Commons; relocation and remodel of Admin and Counseling spaces; relocation of Kitchen and servery; relocation and expansion of L-Café and DECA Store in the new Commons; modernization of 200/300 classroom area; add auxiliary gym and modernize locker rooms; and completion of video/TV labs and production/editing studio.

Contractor:  Babbit Neuman Construction Company

Estimated Completion Date: Phase II spaces occupied September 2013


Liberty High School Addition and Modernization Phase III includes rebuild 400/500 area classrooms including new Library; re-programming and modernization of 600 area classrooms; and repair/replace roofing at existing area outside remodeled areas.

Contractor:  Kassel & Associates

Estimated Completion Date: Phase III spaces occupied September 2014

Project Information
Original Project Estimate:
Project Budget:
Budget: $59,500,000
Explanation:
Funding source: 2012 Bond
Project status: Substantially Complete
Architect: Bassetti Construction
Contractor: See Above
Estimated completion: See Above
Liberty High
Address: 16655 SE 136th Street
Renton, Washington 98059
Principal: Sean Martin
Website: http://connect.issaquah.wednet.edu/high/liberty/default.aspx
Enews: Sign up for Liberty High ENews

Phase II and III April 2017

King County has given final approval for Phase I, II and III projects.

Phase III December 2016

  • Acceptance of Phase III Final Completion is on the 12/14/16 Board Meeting Agenda.

Phase III August 2016

  • Contractor working on punch list items.
  • Finalizing King County paperwork submittals.
  • Work on repairs for the 5100 hallway is complete.

Phase II August 2016

  • Contractor has begun repairing the interior wall in the kitchen. Waiting for wall covering to arrive to finalize work.
  • Contractor working on punch list items.
  • Finalizing King County paperwork submittals.

Phase II July 2016

  • Contractor has begun repairing the interior wall in the kitchen. Waiting for wall covering to arrive to finalize work.
  • Contractor working on punch list items.
  • Finalizing King County paperwork submittals.

Phase III July 2016

  • Contractor working on punch list items.
  • Finalizing King County paperwork submittals

Phase II June 2016

  • Contractor has begun repairing the exterior wall in the kitchen. Waiting for wall covering to arrive to finalize work.
  • Contractor working on punch list items.
  • Reviewing cost proposals.
  • Finalizing King County paperwork submittals.

Phase III June 2016

  • Contractor working on punch list items.
  • Reviewing cost proposals.
  • Finalizing King County paperwork submittals.

Phase II May 2016

  • Contractor has begun repairing the exterior wall in the kitchen.Waiting for wall covering to arrive to finalize work.
  • Contractor working on punch list items.
  • Reviewing cost proposals.
  • Finalizing King County paperwork submittals.

Phase III May 2016

  • Contractor working on punch list items.
  • Last Change Order is being submitted.
  • Finalizing King County paperwork submittals.
  • Commissioning Report has been finalized.

Phase II April 2016

  • Contractor has begun repairing the exterior wall in the kitchen. Waiting for wall covering to arrive to finalize work.
  • Contractor working on punch list items.
  • Reviewing cost proposals.
  • Finalizing King County paperwork submittals.
 

Phase III April 2016

  • Contractor has completed repair work of the classroom sunshades.
  • Tennis court repair work is completed.
  • Contractor working on punch list items.
  • Reviewing cost proposals.
  • Finalizing King County paperwork submittals.
  • Finalizing Commissioning Report.

Phase II March 2016

  • Contractor working on punch list items.
  • Reviewing cost proposals.
  • Finalizing King County paperwork submittals.

Phase III March 2016

  • Contractor working on punch list items.
  • Reviewing cost proposals.
  • Finalizing King County paperwork submittals.
  • Finalizing Commissioning Report.

Phase II February 2016

  • Contractor working on punch list items.

Phase III February 2016

  • Contractor working on punch list items.
  • Science shed waiting for fire sprinkler permit. All other work is completed.

Phase III January 2016

  • Contractor working on punch list items.
  • Science shed waiting for fire sprinkler permit. All other work is completed.

Phase II January 2016

  • Contractor working on punch list items.

Phase II December 2015

  • Contractor working on punch list items.

Phase III October 2015

  • The front entry walkway and planter are complete.
  • Tennis courts are complete.
  • Tennis shed is complete; electrical work to occur the week of October 26th.
  • Science shed is nearly complete; electrical and plumbing work to occur the week of October 26th.
  • Contractor working on completion of punch list items.

Phase III August 2015

  • The front entry planter area sidewalk has been poured, irrigation installed, and trees planted.
  • Tennis courts are completed.
  • Tennis shed is approximately 85 percent completed.  Metal siding to arrive the week of 8/17.
  • Main gym and aux gym wood floors have been refinished and mat room urethane floor recoated.
  • New curtain rails and mirrors have been installed in the Black Box Theater.

Phase III May 2015

  • Kassel and subcontractors are near completion of punch list items
  • ISD working with King County Officials on closing out entire project.
  • The front entry planter area will be completed this summer.
  • Working with King County Officials on finalizing the wood shop spray booth.

Phase II April 2014

  • Contractor working on punch list items.

Phase III December 2014

New Classroom 5000 Wing

  • Commissioning of the mechanical and electrical systems is on-going.
  • Tack boards, vinyl wall covering and Walltalker located in hallways are approximately 98% completed.
  • Irrigation and landscaping work is on-going.
  • Garden wall structural frame in place.  Need to install SS mesh.
  • Rubber tile flooring for the hallways is on-going on weekends.

600 Technology Building

  • Staff items, furniture and equipment have been moved into the art rooms, wood and metal shops and the material science room.
  • Rubber tile flooring for the hallways to start around October 25th.
  • Commissioning of the mechanical and electrical systems is on-going.

Science 1000 Wing

  • Wainscot in hallways have been installed.  Ceiling grid, tiles and lights are installed.
  • Rubber flooring installed is completed.
  • The ADA cabinets have not been stalled.  Waiting for plumbing fixtures. 

Phase II August 2014

  • Contractor working on punch list items.
  • Commons floor refinishing is completed on the main area.  Gymnasium lower floor will start August 25th.

Phase III August 2014

New Classroom 5000 Wing

  • Furniture is being placed in the individual classrooms.
  • Staff items are being placed into classrooms.
  • Library shelving is being installed and books are being placed on shelving.
  • Roofing of the main building is completed. 
  • Metal wall paneling is 98 % completed.
  • Classroom storefront window frames are installed.
  • Elevator is scheduled for final inspection the week of August 27th.
  • King County Building Final inspection is scheduled for August 25th. Partial King County Fire inspection was completed 8/26. Final inspection is scheduled for 8/28.
  • Masonry work is completed.
  • Mechanical units are being started and readied for commissioning.
  • Fire sprinkler system is completed and ready for inspection August 25th and August 28th.
  • Tack boards, vinyl wall covering and Walltalker located in hallways are approx. 85% completed.
  • All rooms and library have been carpeted.  Rubber cove base is complete.
  • All rooms are being cleaned.
  • Electrical trim for lower and upper floor proceeding.
  • Casework is completed in all rooms.
  • Installation of phones and computers has begun.
  • Irrigation work is ongoing.

600 Technology Building

  • Sheetrock is installed and mudding and taping is ongoing.
  • Roofing is completed.
  • Exterior metal siding is approx. 95% complete.
  • Mechanical and electrical rough is approx. 85% complete.
  • Fire sprinkler system is approx. 85% complete.
  • Classrooms 6102 and 6104 are approx. 90% complete and will be ready for use 9/3/14..

Science 1000 Wing

  • Audio Visual system and projectors are approx. 95% completed.
  • Electrical and mechanical trim-out is 98% completed.
  • Wainscot in hallways have been installed.  Need to install chair rail, tack boards and vinyl wall covering.
  • Ceiling tiles are installed.
  • Rooms are being cleaned and readied for furniture delivery.
  • Hallway walls are painted.

Phase III June 2014

New Classroom 5000 Wing

  • Painting is proceeding on both floors and exterior of the 100 Wing.
  • Final roofing of the main building is 90% completed.  Final roofing of the 600 wing has begun.
  • Insulated metal wall panels are approx. 90 percent completed. Corrugated metal panels are completed.
  • Classroom storefront window frames are installed.
  • Library curtain window is installed with glazing.
  • Installation of hollow metal door frames is completed.
  • Hollow metal doors are being primed and painted.
  • Elevator is 90 percent completed.
  • Masonry work is completed.
  • Mechanical units have been installed in the library and 600 Wing penthouses.
  • Ductwork on the lower floor is approx. 95% completed.
  • Classroom HVAC units have been installed.
  • Ductwork on the upper floor is approx. 95% completed.
  • Fire sprinkler lines are approx. 95 percent completed. Fire sprinkler permit submitted in December had not yet been issued by King County.
  • Electrical installation for lower and upper floor proceeding.
  • Casework has begun in the lower south classroom wing.
  • Ceiling grid and fans are being installed in the upper floor north classroom wing
  • Flooring is scheduled to start the first week of August.
  • Site demolition has begun –removal of old sidewalks and paving underway.
  • Irrigation work has begun.

600 Technology Building

  • Sheetrock is installed and mudding and taping is completed
  • Final roofing is approx. 40% completed.
  • Exterior weather barrier is completed.
  • Classroom storefront window frames installed with glazing
  • Masonry work nearly complete.
  • Mechanical and electrical rough in has begun.

Phase II June 2014

  • Contractor working on punch list items.
  • Commons floor refinishing is scheduled for the week of July 7th.

Phase II May 2014

  • Contractor working on punch list items.

Phase III April 2014

New Classroom 5000 Wing

  • Wood framing on lower floor is percent complete.
  • GlueLam beams and wood decking for the library is complete.
  • Placement of sheetrock on the lower and main floor is approximate 20% complete.
  • Metal roof decking is complete.
  • Roofing is approximately 40% complete.
  • Exterior weather barrier is complete.
  • Classroom storefront window frames are installed.
  • Window glazing is approximately 10% complete.
  • Mechanical units have been installed in the library and 600 Wing penthouses.
  • Ductwork on the lower floor is approximately 70% complete.
  • Classroom HVAC units are being installed and are approximately 50% complete.
  • Ductwork on the upper floor is approximately 5% complete.
  • Fire sprinkler lines are 95% complete on the lower floor and 85% complete on the upper floor.
  • Electrical rough-in for lower and upper floor proceeding.
  • Meetings are ongoing with staff on selection of furniture and equipment and preparation for this summer’s move.
  • Capital Project’s Office and consultants are working with the Liberty HS Science staff and students on the design of the green wall.

600 Technology Building

  • Wood framing is approximately 30% complete.
  • Metal roof decking complete.
  • Roofing is approximately 30% complete.
  • Exterior weather barrier is complete.
  • Classroom storefront window frames installed – no glazing.
  • Masonry work is approximately 10% complete.

Phase II October 2013

Administration/Counseling

  • Spaces are occupied.
  • Blinds are installed.
  • Commissioning for mechanical and electrical system underway.

Culinary Arts and DECA

  • Culinary arts room and training is complete.
  • DECA classroom and store are operational.

Athletic Area

  • Electrical and mechanical are working on final trim.
  • Acoustical ceiling tiles have been installed.
  • Weight room and Training room floors are complete.
  • Misc. electrical trim work still in progress.
  • Commissioning for mechanical and electrical system underway.

Commons/Kitchen

  • Kitchen is operational and training has been completed.
  • Commons lights are operational.
  • Acoustical wall panels are complete.
  • Wood paneling is approximately 95 percent complete.
  • Roofing contractor is approximately 90 percent completed with flashing.

Site

  • New ticket booth is approximately 95 percent complete.
  • Plaza around ticket booth is approximately 90 percent complete.
  • Main entry plaza planters are approximately 75 percent complete.

Phase III October 2013

New Classroom 5000 Wing

  • Kassel Construction has completed pouring of footings.
  • Footing drains are being installed.
  • Below grade waterproofing is approximately 30 percent complete.
  • Underground plumbing is complete.
  • Power, data and intercom are operational in the Tech building.
  • Underground electrical is 95 percent complete.
  • Vapor barrier has been installed at all slabs on grade locations.
  • Concrete floors are scheduled to be poured the week of October 21st      

Science Lab and ASB Room

  • Science room and ASB room are complete and occupied. Wall covering for the ASB room is to arrive the week of October 28th and the new display cabinet will arrive the week of November 4th.  Contractor has completed punch list items, excluding the two listed.

Phase II September 2013

Administration/Counseling

  • Spaces are occupied
  • Blinds are scheduled to be installed the week of October 7th.
  • Commissioning for mechanical and electrical system underway.

Culinary Arts and DECA

  • Culinary arts room is scheduled for completion around October 7th.
  • DECA classroom and store are operational

Athletic Area

  • Mechanical units are installed in the new penthouse.
  • Electrical and mechanical are working on final trim.
  • Acoustical ceiling tiles will be installed the week of October 1st.
  • Weight room and Training room floors are complete.
  • Misc. Electrical trim work still in progress.
  • Commissioning for mechanical and electrical system underway.

Commons/Kitchen

  • Kitchen is operational with the exception of the equipment under the hood.
  • Kitchen hood scheduled for commissioning Sept. 26th.
  • Contractor is scheduled for final completion of the kitchen October 7th.
  • Commons lights are operational.
  • Acoustical wall panels are approximately 85 percent complete.
  • Wood paneling is approximately 95 percent completed.
  • Temporary construction wall between auditorium and commons has been removed.
  • Roofing contractor is approximately 90 percent completed with flashing.

Site

  • New ticket booth is approximately 70 percent completed.
  • Plaza around ticket booth is approximately 85 percent complete.
  • Main entry plaza planters are approximately 75 percent complete.

Phase III September 2013

New Classroom 5000 Wing

  • Kassel Construction is proceeding with placement of footings.They are approximately 50 percent complete.
  • Footing drains are being installed.
  • Underground plumbing is approximately 40 percent complete.
  • Power, data and intercom are operational in the Tech building.
  • Underground electrical is 95 percent complete.

Science Lab and ASB Room

  • Science room and ASB room are complete and occupied.  Consultants are scheduled to come out next week to do their punch list.

Phase II August 2013

Administration/Counseling

  • Staff has moved in to their new office spaces

 

Culinary Arts and Marketing

  • Tiling is complete in the Culinary Arts room.
  • Kitchen equipment is arriving on site the week of August 12th.
  • Casework has been completed in the marketing classroom.
  • Casework for the student store will be installed.

 

Athletic Area

  • Walls are painted and wainscot is being installed in hallways.
  • Wood floor installation is in progress.
  • Floor prep has begun for new flooring.
  • Windows have been installed.
  • Metal siding is near completion.
  • Mechanical units are installed in the new penthouse.
  • Electrical and mechanical are working on final rough in.
  • Casework has been completed in the training, fitness and PE offices.
  • Display cabinets and benches are being installed in the gym foyer.
  • Tiles in the public restrooms are complete.

 

Commons/Kitchen

  • Mechanical units have been installed in the penthouse.
  • Walls in the Commons are be prepped for final finishes.
  • Waterproofing of exterior walls in near completion.
  • Chillers have been installed.
  • Windows have been installed.
  • Quarry tiles are installed in the kitchen.
  • Walk-in cooler and freezer are installed. Need to complete electrical and mechanical.
  • Kitchen equipment is on site and being installed.

 

Site

  • New ticket booth is approx. 70 percent complete. 
  • Plaza around ticket booth is approx. 85 percent complete.
  • Main entry plaza planters are approx. 75 percent complete.

Phase III August 2013

New Classroom 5000 Wing

  • Hazardous material abatement is complete.
  • Demolition is in progress, they are approximately 90 percent complete.
  • Earthwork contractor is proceeding with installing valves and back flow preventers on the fire and domestic water lines.
  • Contractor is pouring new concrete curbs and backfilling for the future staff parking stalls the week of August 12th

Science Lab and ASB Room

  • New science lab & ASB Classroom inspection complete, drywall to begin.

Phase II May 2013

Administration/Counseling

  • Staff has moved in to their new office spaces

Culinary Arts and Marketing

  • Tiling is complete in the Culinary Arts room.
  • Kitchen equipment is arriving on site the week of August 12th.
  • Casework has been completed in the marketing classroom.
  • Casework for the student store will be installed.

Athletic Area

  • Walls are painted and wainscot is being installed in hallways
  • Wood floor installation is in progress
  • Floor prep has begun for new flooring
  • Windows have been installed
  • Metal siding is near completion
  • Mechanical units are installed in the new penthouse
  • Electrical and mechanical are working on final rough in
  • Casework has been completed in the training, fitness and PE offices
  • Display cabinets and benches are being installed in the gym foyer
  • Tiles in the public restrooms are complete.

Commons/Kitchen

  • Mechanical units have been installed in the penthouse
  • Walls in the Commons are be prepped for final finishes
  • Waterproofing of exterior walls in near completion
  • Chillers have been installed
  • Windows have been installed
  • Quarry tiles are installed in the kitchen
  • Walk-in cooler and freezer are installed.Need to complete electrical and mechanical.
  • Kitchen equipment is on site and being installed.

Site

  • New ticket booth is approx. 70 percent complete 
  • Plaza around ticket booth is approx. 85 percent complete
  • Main entry plaza planters are approx. 75 percent complete

Phase III May 2013

  • Bidding documents for Phase III are on the street.  Bid date is May 21, 2013 at 2:00 PM.

Phase II March 2013

  • Sheetrock for the administration and counseling areas is complete.
  • Electrical rough-in for the administration and counseling areas is complete.
  • Window frames are in for the administration and counseling areas.Glazing is complete in the counseling areas.
  • Roofing is 90 percent complete for the administration and counseling.
  • HVAC ducts are 90 percent complete in the admin and counseling offices.
  • Fire Sprinkler lines are 90 percent complete in the admin and counseling offices.
  • Earthwork contractor has completed grading for the commons and kitchen area.The plumber and electricians are working on under-slab utilities. Floor slab has been poured in some areas of the commons.
  • Steel erectors have completed the athletic area and they are 45 percent completed with the commons area.
  • Framing for the athletic areas is 75 percent complete
  • Roofers have started on the athletic wing roof
  • Electrical and mechanical under slab utilities is completed in the locker area.Electrical and plumbing rough in is 90 percent completed.
  • Acoustical wall panels are being erected in the theater; they are about 40 percent complete.

Phase III March 2013

  • Design is proceeding. Staff from Bassetti Architects and Capital Projects has met with school staff on the use of their individual spaces and their needs.
  • Bid opening planned for late May.

Phase II February 2013

  • Framing for the administration area is complete and sheetrock is approximately 85 percent complete.
  • Electrical rough-in for the administration and counseling areas is 90 percent complete.
  • Under slab plumbing and electrical for the kitchen and “L” Café are complete.
  • Concrete has been placed at the stairs leading to the lower athletic areas, second floor of the athletic area, stairs at the commons entrance.
  • Contractor has started forming footing for the kitchen.
  • The existing ticket booth has been demolished. Grading has started and digging for footings is underway.
  • Structural columns for the second floor to the athletic area are complete. Roof trusses are being placed.
  • Roofing on the administration and counseling areas is approximately 40 percent complete.
  • Air and moisture barrier is being applied to the administration and counseling exterior walls.

Phase III February 2013

  • The Architect has submitted construction documents to King County Building Department for permitting.
  • Design is proceeding. Staff from Bassetti Architects and Capital Projects has met with school staff on the use of the individual spaces needs.

Phase II January 2013

  • Framing for the administration area is 90 percent completed.
  • Electrical rough-in for the admin is 60 percent completed.
  • Framing for the counseling area is 80 percent completed.
  • Under slab plumbing in admin and counseling is completed.
  • Earthwork contractor has completed grading for the commons and kitchen area.  The plumber and electricians are working on under slab utilities.
  • Contractor has started forming footings for the east commons area and is moving westward.
  • Locker room masonry walls are completed
  • Electrical and mechanical under slab utilities is completed in the locker area.  Electrical and plumbing rough in is 90 percent completed.

Phase III January 2013

  • The Architect and District rep’s meet with King County officials for the pre application the week of December 17th.  Application for permit is scheduled the latter part of January.
  • Design is proceeding.  Staff from Bassetti Architects and Capital Projects have met with school staff on the use of their individual spaces and their needs.

Phase II November 2012

  • Structural steel erection has started in the administration area. Concrete slab for the administration extension is completed. Concrete masonry units being placed along the south admin wall.
  • Below slab electrical and plumbing in the administration and counseling areas is complete.
  • Below slab electrical and plumbing in the locker rooms and new gym entry hallway is proceeding.They are approximately 60 percent complete.
  • Final connection to the gas meter is complete.
  • Footings for the locker rooms and gym entry hallway are complete.
  • Formwork for the concrete walls is approximately 80 percent complete.
  • Placement of the new CMU wall for the gym entry hallway is approximately 80 percent complete.

Phase III November 2012

  • Bassetti Architects and staff from the Capital Projects office have been meeting on a regular basis with LHS staff to review current plans for both Phase III and the Stadium.

Phase II September 2012

  • The locker rooms, weight room, commons, kitchen have been completely demolished. Selective demolition in the counseling and administration areas is completed.
  • Rough grading is approximately 50 percent completed.
  • Footings in the admin area are approximately 50 percent completed.
  • The deep footings for the future weight/fitness rooms have been poured.

Phase II May 2012

  • Phase II walk through for contractors was held on May 14th.  At this time, there are five contractors interested in the project.
  • Coordination of Phase II move with staff is ongoing.
  • Preparation and coordination of summer work to ready the school for the start of Phase II continues.Start of conversion work begins the day after school is out.
  • Phase II work is scheduled to go out to bid May 7th.We plan to have the Authorization of Notice of Intent to Award on the June 13th Board Meeting Agenda.