Bond Projects

Elementary #17

E17
To meet continued enrollment growth, the District will construct a new elementary school to house up to 650 students. The building will include 23 classrooms and construction of playfield, bus and circulation areas and new parking.

Elementary School #17 is currently planned to be located on the same site as the new High School #4.  The proposed site is located at 4200 - 228th Ave. SE, Issaquah, WA 98029 (former location of the Providence Heights College).

Project Information
Original Project Estimate: $38,000,000
Project Budget: $38,000,000
Budget: $38,000,000
Explanation:
Funding source: 2016 Bond
Project status: Planning, Design, and/or Permitting
Architect: Bassetti Architects
Contractor: Skanska
Estimated completion: September 2022

October 2020

  • SDP Application and MSP Applications were submitted 09/25/2020 and deemed complete applications on 10/06/2020. Public comment period is complete 11/19/2020.
  • The design team and ISD continue to meet with City Staff to work through the issues of the FAR, retaining wall height and tree-save.
  • The Design Team continues to work and design the site, the buildings, etc. to make everything as efficient as possible.

September 2020

  • Submittal of the SDP Application and MSP Application is scheduled for 09/25/2020.
    • Submittal was delayed in an attempt to leverage information learned and City Councilmembers comments from the 9/15 City Council Study Session to further our discussions with City Staff concerning the FAR portion of City code prior to application.
  • The Design Team continues to work and design the site, the buildings, etc. to make everything as efficient as possible.

August 2020

  • Completion of responses to the Community Conference are nearing completion. Working with City Staff on final report.
  •  ISD and the Design-Build Team submitted the application for the Site Development Plan (SDP)/Master Site Plan (MSP) in early September.
  • ISD staff and the Design Team continue to work with the COI staff to move the SDP/MSP permitting process along.
  • The Design Team continues to work and design the site, the buildings, etc. to make everything as efficient as possible.

June 2020

  • City of Issaquah has scheduled the Community Conference for July 15, 2020 @ 6:30 p.m.
  • ISD and the Design-Build Team submitted the application for the Site Development Plan (SDP)/Master Site Plan (MSP) Thursday May 28th.
  • ISD staff and the Design Team continue to work with the COI staff to move the SDP/MSP permitting process along.
  • The Design Team continues to work and design the site, the buildings, etc. to make everything as efficient as possible.

January 2020

  • No changes.

November 2019

  • ISD design team and the City of Issaquah staff are working through configurations to narrow down the site, parking and building layout.
  • ISD design team continuing to refine the building designs.
  • ISD and the City planning department are working on rezoning to enable the site to accommodate schools.

April 2018

Site acquisition remains underway.
No photos galleries are available for this project.
No additional documents are available for this project.