Skip to Page Content Skip to the search box and translation tools

Bond Projects

2016 Bond Projects Current Budget Status
Beaver Lake Middle School Upgrade/Update To Be Determined Planning, Design, and/or Permitting Estimated completion date September 2021
Central Administration Building 12000000 Substantially Complete With remodel and tenant improvement substantially complete, Issaquah School District administration staff moved into their new office location in July 2019.  
Cougar Ridge Expansion Project 13000000 Substantially Complete On track for Substantial Completion September 5, 2018
Discovery Elementary Expansion/Remodel 9000000 Under Construction Bid Date June 2018; Estimated Completion September 2019
Elementary #16 36500000 Planning, Design, and/or Permitting  
Elementary #17 38000000 Planning, Design, and/or Permitting
Endeavour Expansion/Remodel 9000000 Under Construction

Bid Date June 2018; Estimated Completion September 2019

Maple Hills Expansion/Remodel To Be Determined Planning, Design, and/or Permitting Estimated completion date Summer 2021
New High School #4 120000000 Planning, Design, and/or Permitting Estimated completion date of September 2021 dependent on land acquisition.
New Middle School #6 To Be Determined Planning, Design, and/or Permitting Estimated completion date September 2021
Pine Lake Middle School Rebuild 72000000 Substantially Complete On track for Substantial Completion September 5, 2018
Sunset Expansion Project 9000000 Substantially Complete On track for Substantial Completion September 5, 2018
2012 Bond Projects Current Budget Status
Apollo and Issaquah Valley Expansion Projects 15375000 Final Acceptance Project was approved as Final by the Issaquah School District Board of Directors on February 8, 2017.
Clark Elementary School Rebuild 41035000 Substantially Complete Project was Substantially Complete on August 16, 2017.
Gibson Ek High School 6150000 Substantially Complete Date of Substantial Completion was 8/30/16.
Issaquah Middle School Rebuild 63500000 Substantially Complete The building met Substantial Completion on 8/16/2016.
Liberty High School Addition and Modernization Phase II and III 61620000 Final Acceptance

Phase II work approved as Final by the Issaquah School District on February 28, 2019.

Phase III work approved as Final by the Issaquah School District Board of Directors on December 14, 2016.

Liberty High School Grandstand Project 4875000 Final Acceptance Date of Substantial Completion was 8/15/16.  The project was accepted as Final on 9/6/2016.
Middle School Turf Field & Track Improvements 11125000 Final Acceptance The projects were approved as Final by the Issaquah School District Board of Directors on January 10, 2018.
Skyline High School Grandstand & Stadium Project 11025000 Final Acceptance The Grandstand was accepted as Final on 8/22/16.  Substantial Completion for Stadium was 10/28/2016 and accepted as Final on 8/1/2017.
Sunny Hills Elementary School Rebuild 35500000 Final Acceptance The building was approved as Final by the Issaquah School District Board of Directors 9/27/17.
2006 Bond and Levy Projects Current Budget Status
Briarwood Elementary Rebuild 26285000 Final Acceptance The project was approved as Final by the Issaquah School District Board of Directors on February 10, 2016.
Creekside Elementary (E15) 23544000 Final Acceptance The project was approved as Final by the Issaquah School District Board of Directors on November 9, 2011.
Issaquah High School Reconstruction 96225000 Final Acceptance The project was approved as Final by the Issaquah School District Board of Directors November 28, 2012.
Liberty High School Addition and Modernization Phase I 24850000 Final Acceptance The project was accepted as Final by the Issaquah School District Board of Directors on April 23, 2014.
Maywood Middle School Addition & Modernization 25940000 Final Acceptance Maywood Modernization and Maywood Building/Mechanical Upgrades are Final. The Maywood Classroom Infill Project is Substantially Complete.