Bond Projects

2016 Bond Projects Current Budget Status
Cougar Ridge Expansion Project $9,000,000 Planning and/or Design
Pine Lake Middle School Rebuild $70,000,000 Under Construction
Sunset Expansion Project $7,000,000 Planning and/or Design
2012 Bond Projects Current Budget Status
Apollo and Issaquah Valley Expansion Projects $15,350,000 Final Acceptance Project was approved as Final by the Issaquah School District Board of Directors on February 8, 2017.
Clark Elementary School Rebuild $36,500,000 Under Construction
Gibson Ek High School $5,950,000 Substantially Complete Date of Substantial Completion was 8/30/16.
Issaquah Middle School Rebuild $64,000,000 Substantially Complete The building met Substantial Completion on 8/16/2016.
Liberty High School Addition and Modernization Phase II and III $59,500,000 Substantially Complete Phase II work is not Final.  Contractors continue to work on punchlist items. Phase III work approved as Final by the Issaquah School District Board of Directors on December 14, 2016.
Liberty High School Grandstand Project $4,875,000 Substantially Complete Date of Substantial Completion was 8/15/16.
Middle School Turf Field & Track Improvements $10,000,000 Substantially Complete
Skyline High School Grandstand & Stadium Project $10,000,000 Substantially Complete Date of Substantial Completion for Grandstands was 8/15/16.  Substantial Completion for Stadium was 10/28/2016.
Sunny Hills Elementary School Rebuild $35,200,000 Substantially Complete The building met Substantial Completion on 8/26/2016.  The contractor continues to work on punch list items.
2006 Bond and Levy Projects Current Budget Status
Briarwood Elementary Rebuild $26,285,000 Final Acceptance The project was approved as Final by the Issaquah School District Board of Directors on February 10, 2016.
Creekside Elementary (E15) $23,520,000 Final Acceptance The project was approved as Final by the Issaquah School District Board of Directors on November 9, 2011.
Issaquah High School Reconstruction $96,225,000 Final Acceptance The project was approved as Final by the Issaquah School District Board of Directors November 28, 2012.
Liberty High School Addition and Modernization Phase I $24,850,000 Final Acceptance The project was accepted as Final by the Issaquah School District Board of Directors on April 23, 2014.
Maywood Middle School Addition & Modernization $25,940,000 Final Acceptance Maywood Modernization and Maywood Building/Mechanical Upgrades are Final. The Maywood Classroom Infill Project is Substantially Complete.